Processing | Time |
Prepare Steel | 5 days |
CNC Machining | 10 days |
Drill | 8 days |
Heat treatment | 6 days |
High speed CNC Machining | 7 days |
Assembling and Fitting | 6 days |
Polishing | 6 days |
T1 mould test | 2 days |
1. Samples/Drawing & Requirement from you | |
2. Mould design: we will Communicate& Exchange the opinion with you after you place order. | |
3. Material Purchase: Steel cutting and Mould base tooling. | |
4. Assembling. | |
5. Inspection of mould: following and controlling the tooling processing. | |
6. Mould testing: We will inform you the date. Than will send the sample' s inspection report& injection parameters with the sample to you! | |
7. Your instruction & confirmation for shipment. | |
8. Ready made mould before packing. |